Robotic Cleaning of Ethylene Heater Convection Banks Leads to Substantial Performance Increase

Rapid response adds to higher margins

A Netherlands based petrochemical needed to remove fouling from the external surfaces of their finned convection tube banks. Bespoke Robotic technology achieve a quick and significant performance increase for the client.

  • The Fired Heater / Furnace constructed with finned and bare convection tube banks.
  • Cleaned alongside a 'live' furnace so access and heat had to be overcome.
  • Compacted hydrocarbon and refractory deposits combined with friable scale coating the majority of convection tubes and fins.
  • Thickness of deposit up to 5mm with some bridging between tubes and fins.
  • Increased fouling on lower banks having dropped from upper sections.
  • Had to be cleaned quickly as plant needed welding repairs before start up.
  • Robots required rapid re-configuration in order to clean various convection bank designs.
  • Access to furnace solved by use of cat ladders and removing floor.
  • Mobilisation in under 10 days from enquiry, robot modification, to start.

Assistant Maintenance Supervisor comments:

“Hereby my reference for the cleaning the convection section of our furnace. To summarize it short, it was a very successful job. Thank you for your work.

Safety is very important and Tube Tech proved to be aware of all safety requirements and worked accordingly. Applying a high safety standard themselves and open to suggestions for improvement. The job was executed without any safety issues.

The convection tubes cleaned by your robots contributed to the performance increase. For the same furnace severity (P/E ratio) with similar burner condition (measured O2 level in stack) we see an increase of feed throughput. In addition, a cleaner convection also see a higher efficiency burner. Improvement of 16 deg C in stack temperature means more burning efficiency. That adds up the higher obtained margin.

The cleaning job executed was an opportunity driven by already unplanned furnace outage. Tube Tech managed to be able to mobilize and be on site 1.5week after our first meeting. Furthermore, the execution of the job was smoothly. It is a considerable task to perform all the cleaning in only 5 days; even with some setbacks due to weather. The team managed to keep focused to make up for the time lost and managed to finish the job in the agreed time window.

The costs stayed within the agreed price up front. No additional costs were made. However, Tube Tech is more expensive than our house cleaning contractor, the specialized technique makes up for it. The improved performance of the furnace justified the higher costs.”

Related Case Studies

Lorem ipsum dolor sit amet, consectetur adipiscing elit. Praesent sit amet nisl nec elit dictum tincidunt quis vitae nunc. Duis aliquam malesuada erat, quis consectetur justo varius vitae. Praesent faucibus est quis ipsum vestibulum finibus. Maecenas et ex id nibh imperdiet imperdiet. Morbi bibendum vel erat sit amet elementum.

Tube Tech Restores Convection Section at Petrochemical Plant in Bangkok

Read More

A 'Bonny' Trip To Nigeria

Read More

Cleaning Ethylene Radiant Furnace Tubes

Read More

Furnace cleaning of a German refinery using Robots – a world first

Read More

Furnaces / Fired Heater Convection Bank Cleaned Robotically on German Refinery

Read More

Robotic Ethylene Fired Heater Convection Bank Cleaning in The Netherlands

Read More

Massive Cost Saving by Avoiding Convection Section Replacement After Robotic Clean

Read More

Furnace / Fired Heaters Tube decoking ON-LINE! at Distillate Synthesis Plant in Malaysia – World First!

Read More

Fired Heater / Furnace Coils Cleaned Cleaned in Trinidad

Read More

Fired Heaters Tubes (Finned Convection)

Read More

TTIL Delivers Instant ROI for Global Oil and Gas Giant

Read More

TTIL’s pioneering technology restores optimum heat duty at Australian ammonium nitrate facility

Read More

Tube Tech International Increases Productivity at Leading Petrochemical Plant in the Middle East

Read More

Robotic Fired Heater Cleaning of Finned Convection Tubes

Read More

Robotic Fired Heater Convection Bank Cleaning in Trinidad

Read More

Robotics Restore Heavily Fouled Heater

Read More

TTIL Robots Restore Convection Sections at U.S. Petrochemical Plant

Read More

Tube Tech Provide Robotic Cleaning Solution for Netherlands Plant - The Only Solution!

Read More

Furnace / Fired Heaters Tubes (USX/TLX) Cleaned in Record Time

Read More

Free Quote - 24 Hour Response

Send us your enquiry below and a Tube Tech International specialist will respond within 24 hours. Regardless of your industry sector or severity of fouling, we will have a solution to deliver guaranteed results.